Masores Avos
Large View

Masores Avos

23 South Congress Street, Lakewood NJ 08701

Project Goals

Creation of a large-scale addition to existing school building to accommodate school functions and outside events
  • Extensive school building addition
Project Duration
  • 22 months
  • Start Date: November 2016
  • Occupancy Date: September 2018

Overview

To keep school in session during the building’s reconstruction, Regency formulated a complex plan, working in sections. As each third of the aging structure was rebuilt, it was integrated with the other sections. Maintaining structural integrity throughout this re-engineering process required persistence and versatile skills.