23 South Congress Street, Lakewood NJ 08701Project Goals
Creation of a large-scale addition to existing school building to accommodate school functions and outside events
- Extensive school building addition
Project Duration
-
22 months
-
Start Date: November 2016
-
Occupancy Date: September 2018
Overview
To keep school in session during the building’s reconstruction, Regency formulated a complex plan, working in sections. As each third of the aging structure was rebuilt, it was integrated with the other sections. Maintaining
structural integrity throughout this re-engineering process required persistence and versatile skills.