Bnos Esther Malka

Bnos Esther Malka

488 Whitesville Road, Lakewood NJ 08701

Project Goals

Develop a highly customized new building for a fast-growing girls’ elementary school in under a year
  • 46,000 SF 3-story school building being built in phases
Project Duration
  • 12 months
  • Start Date: October 2017
  • Occupancy Date: September 2018

Overview

This project had the logistical challenges of a mammoth Rubik’s Cube. Since it’s situated on an incline, the plans called for multiple levels of excavation, interior construction and points of entrance/egress for both the front and back levels.
 
This challenge was intensified by the proximity to neighbors. The team was careful to work within the confines of the tight space without compromising nearby properties.
 
Tight space, tight timetable — but wide smiles on opening day in September 2018.