613 Oak Street, Lakewood, NJ 08701Project Goals
Creation of 75,000 SF state-of-the-art, 27-classroom school campus
- 75,000 SF school building
- 2 stories plus basement
Project Duration
-
18 months
-
Start Date: April 2010
-
Occupancy Date: September 2011
Overview
Extensive building plans included 27 classrooms, offices, auditorium, lunchroom and kitchen, full parking lot with recharge and drainage system and split-faced block exterior walls with stucco front. Regency’s team had to overcome significant municipal and logistical hurdles to breathe life back into the site. The team proposed adding an additional bearing wall in the basement thus saving a substantial amount on floor trusses. Plans were reviewed and redesigned with the architect, and the savings were passed on to the client.